PDR Usually accomplished in the Development, Type B
Demonstration and Validation Performance
and/or Full Scale Specification,
Development Phase Drawings Level
I DOD-D-1000,
Software Top Level
Design Document,
Software Test Plan,
Preliminary Computer
Resources Integrated
Support Document,
Preliminary Computer
System Operator's
Manual, preliminary
Software User's
Manual, preliminary
Computer System
Diagnostic Manual.
CDR Usually accomplished in the Draft Product, Type
Full Scale Development C Specification and
Phase referenced
Documentation,
Drawings Level I or
II DOD-D-1000,
Software Detailed
Design Document,
Interface Design
Document(s), Data Base
Design Document(s),
Software Test
Description, Computer
Resources Integrated
Support Document,
Software Programmer's
Manual, Firmware
Support Manual,
Informal Test
Descriptions/Test
Procedures, Software
Development File(s).
TRR Usually accomplished in Software Test
The Full Scale Development Procedure, Informal
Phase software test results
(of development
Tests).
FCA Usually accomplished at Test plans, test
End of Full Scale descriptions, test
Development procedures, Software
Test Reports, Computer
System Operator's
Manual, Software
User's Manual,
Computer System
Diagnostic Manual.
PCA Usually accomplished early Final Part II
in the initial production Specification/Type C
When the developing Product Specifications
Contractor is preselected and referenced
As the production documents and
Contractor. However, may drawings. Drawings
Be accomplished at the end Level II or III
Of Full Scale Development DOD-D-1000. Software
When the developing Product Specification,
Contractor is not Version Description
Preselected as the Document.
Production contractor.
And the PCA is repeated
With each subsequent
Contractor or break in
Production.
Although the time frame for reviews and audits is suggested above, they may vary depending on the particular program. The schedule for each review or audit may be requested from the offerer as part of his proposal, or as part of the system engineering management plan (which can be part of the proposal).
APPENDIX K
PRODUCTION READINESS REVIEW
Production Readiness Review (PRR)
For specific guidance, see AFSCR 84-2, Production Readiness Review.