Home Random Page


CATEGORIES:

BiologyChemistryConstructionCultureEcologyEconomyElectronicsFinanceGeographyHistoryInformaticsLawMathematicsMechanicsMedicineOtherPedagogyPhilosophyPhysicsPolicyPsychologySociologySportTourism






Bar chart of the sequence of trades on a building site

 

Trade: steel erectors Trade: cladding fixers

Job: erecting the steelwork Job: fixing the cladding

Weeks working: 9 to 15 Week working: 16 to 30

 


 




 


 

Trade: bricklayer

Job: building the brickwork

Weeks working: 13 to 21

the steel

During weeks 13, 14 and 15

From the beginning of week 13 to the end of week 15

erectors work bricklayers.

 

While the former erect the steelwork, the latter build the brickwork.

As soon as

Immediately after the steel erectors have finished, the cladding

fixers begin.

Use the bar chart to help you label the following drawings. Then make similar paragraphs:


 


 

a)Trade: ……. Trade:…………….

Job:………. Job:………

Weeks working:…….. Weeks working:……..

 


 




 

 

 


Trade: …..

Job: ……. Weeks working:……..

 


b) Trade:_______

Job:…......

Weeks working:…….

Trade:_______

Job:......

Weeks working:……

Trade:_______

Job:......

Weeks working:……

c) Trade:_______

Job:…......

Weeks working:…….

Trade:_______

Job:…......

Weeks working:…….

Trade:_______

Job:…......

Weeks working:…….

 

d) Trade:_______

Job:…......

Weeks working:…….

 

 

 

Trade:_______ Trade:_______

Job:…......

Weeks working:……. Job:…......

Weeks working:…….

II.Read this:

While the steelwork is being erected, some of the brickwork is built.

Now look at the bar chart and make similar sentences.

III.Complete these sentences with the name of a building trade:

a)The……._ finish just before the plumbers start.

b) The....... should finish by the end of week 40.

c) The…….. …….. work until the end of week 30.

d) The…….. work up to the end of week 50.

e) The…….. ……. should finish no later than the end of

week 8.

Now make similar sentences.

IV.Read this:

During building construction, several things went wrong so there are several changes to be made to the barchart in exercise 5. Here is a description of what happened: Excavation was delayed for two weeks because the excavator broke down. Therefore the machine drivers could not start work until week 3. As the steel erectors had to wait until the machine drivers hadcompleted their work, they were also delayed by two weeks. Consequently, the cladding fixers could not start until week 17. Bricks were in short supply during weeks 15 to 20 and this resulted in thebricklayers working three weeks longer than expected. So the plumbers and the roofing con­tractor started three weeks later. In week 30 the joiners went on strike which was settled after one week. However,this meant both the carpenters and the glaziers started one weeklate. The wrong paint was delivered to the decorators, which delayed them by one week, but by putting on extra men thebuilding was completed on schedule.

 

Now draw a new bar chart using the information in the passage.



V. Make a list of other things that could go wrong ona building site. Say when they might occur and how they could affect the time schedule.

 

Lesson 14


Date: 2015-12-24; view: 1909


<== previous page | next page ==>
Give the full answer. | The tools and instruments used in building construction.
doclecture.net - lectures - 2014-2024 year. Copyright infringement or personal data (0.006 sec.)