TABLE – HAZARD IDENTIFICATION

Exercise 03 – International airport construction work

Scenario

This is a construction project to repave one of the two crossing runways at an international airport (100,000 movements a year). It’s a three-phase construction project.

 

Scope of the work

· Phase 1:

o Extend the length of RWY 09-27 by 900 meters westward and width from 30 to 45 meters from intersection with RWY 18-36, and strengthen the runway extension (from asphalt to concrete) to increase its Pavement Classification Number (PCN).

o Extend the length of TWY Delta by 900 meters westward.

o Estimated time to complete the work: seven (7) months.

· Phase 2:

o Construct and enlarge new threshold entrance and holding zone at TWY Charlie.

o Extend the width of RWY 09-27 from 30 to 45 meters and strengthen (from asphalt to concrete) this part of the runway up to a point 200 m before intersection TWY A-B to increase its PCN.

o Estimated time to complete the work: five (5) months.

· Phase 3:

o Complete the construction work of RWY 09-27 for the central area of the last 350 m at the intersection of RWY 09-27 and RWY 18-36 (from asphalt to concrete), increase its width from 30 to 45 meters and its PCN.

o Estimated time to complete the work: two (2) months.

· Runway utilization during the construction work

o Continuous utilization of RWY 18-36 during the three-phase construction project.

o RWY 18-36 length is 3.850 m and the distance available from threshold RWY 18 to intersection RWY 09-27 is 2.600 m.

o Information must be provided to airport users.

Group activity

A facilitator will be appointed, who will coordinate the discussion. A summary of the discussion will be written on flip charts, and a member of the group will brief on their findings in a plenary session.

Your task

1. Identify the hazards using brainstorming techniques.

a. Brainstorm a list of possible hazards (use a flip chart).

b. Make sure they are hazards, not risks.

2. Complete the attached log (Table) as follows:

a. List type of operation or activity

b. State the generic hazard (hazard statement)

c. Identify specific components of the hazard

3. It is recommended to conduct the analysis per phase of construction.


TABLE – HAZARD IDENTIFICATION

Type of operation or activity State the generic hazard (hazard statement) Identify specific components of the hazard
Air Traffic Services Air traffic considerations associated with single runway operation. - Increased volume of traffic - Separation issues - Runway congestion - Controller workload - …
Airport operations
Airlines (flight operations)




Date: 2015-12-11; view: 1052


<== previous page | next page ==>
ENGLISH HALLOWEEN CUSTOMS | Risk assessment matrix
doclecture.net - lectures - 2014-2024 year. Copyright infringement or personal data (0.007 sec.)